How the numbers are calculated, and where prices come from.

Volume math is geometric. Bag yields come from manufacturer data sheets. Ready-mix and installed prices are published ranges that do not always agree, so we present the range and name every source. Last reviewed November 19, 2026.

PadCalc shows its work. Volume math is geometric. Bag yields come from manufacturer data sheets. Prices are published national (or named-metro) ranges. When sources disagree, we present the disagreement. Last reviewed November 19, 2026.

Volume formulas

One cubic yard is 27 cubic feet. Coverage for a loose cubic yard is 324 ÷ depth in inches square feet (because 27 ÷ (depth in inches ÷ 12) = 324 ÷ depth). All results start in cubic feet, then divide by 27 when we report yards.

Worked example: a 10 × 10 ft slab, 4 inches thick, is 10 × 10 × (4 ÷ 12) = 33.33 ft³ = 1.23 cubic yards before waste (33.33 ÷ 27 = 1.234…, rounded to two decimals).

We do not copy a typo that has appeared on some coverage explainers (“one cubic foot equals 3.7 cubic yards”). That statement is false; one cubic yard equals 27 cubic feet.

Waste and overage

Where a calculator has a waste field, you can add a percentage to the plan volume. A 10% default, when we use one, is a planning allowance you can change, not a hidden “industry standard” we attributed to a handbook we could not read.

Use the lower end for regular, accurately formed work, and more when excavation or forms are uncertain. Recheck remaining volume near the end of a pour, as CIP 31 also advises. For gravel, mulch, pavers, deck boards, and tile, waste is likewise your allowance — we did not find a single cited standard that we were willing to hard-code as if it were code.

Bag yields

Bag counts for standard concrete mix use the published yields for QUIKRETE Concrete Mix, product no. 1101:

Bag sizeYieldBags per cubic yard (before waste)
80 lbapproximately 0.60 ft³45
60 lbapproximately 0.45 ft³60
50 lb Fast-Setting0.375 ft³72

Sources: QUIKRETE Concrete Mix data sheet, product no. 1101 (80 and 60 lb). The same 80 lb yield (0.60 ft³; 45 bags per yard) is also stated on the Home Depot product listing for QUIKRETE 80 lb Concrete Mix. The 50 lb Fast-Setting yield is from the QUIKRETE Fast-Setting Concrete data sheet. Order volume in cubic feet is divided by the yield, then rounded up to a whole bag. Specialty mixes can yield differently — use the number printed on the bag you buy.

The Fast-Setting sheet also says two 50 lb bags “will set a 3 in square post in a 9 in diameter hole 30 in deep.” A geometric fill of that hole, after subtracting the post, is a little over two bags (about 0.95 ft³, or three 50 lb bags when we round up). The fence-post calculator shows the geometry and quotes the two-bag rule of thumb; it does not force the count to two.

Ready-mix prices (2026 guides)

These figures are for concrete and typical delivery, not labor, forms, base, reinforcement, or pumping. National guides disagree, so PadCalc does not pick a single mid-point. The concrete calculator’s planning range is the span of the published lows and highs below: $110–$195 per cubic yard.

SourceDatedPublished rangeWhat it covers
Angi, “Concrete Cost Per Yard [2026 Data]” September 10, 2026 $110–$150 per yd³ (about $130 average) Concrete delivery cost per cubic yard. A truckload of about 10 yd³ is listed at $1,100–$1,440.
HomeGuide, “How Much Does Concrete Cost Per Yard? (2026)” by Tom Grupa January 6, 2026 Base price $119–$147 per yd³ Includes delivery up to 20 miles. The page also lists a hero range of $119–$172 for “delivered & poured,” which we do not use for the material estimate because it may include pouring.
Concrete Network, “Concrete Prices 2026” by Sarah Hutchinson July 14, 2026 $160–$195 or more per yd³; 2025 national average $179.95 Nationwide ready-mix range. The $179.95 average is attributed to Concrete Financial Insights. Regional snapshots on the same page include Chicago about $183, Los Angeles about $182, and Lynchburg, VA about $165.

Your local plant can quote outside this span. Prices vary by region, mix strength (PSI), delivery distance, season, and order size.

Short-load and other add-ons

These are shown as separate notes in the concrete calculator when the order is under 10 cubic yards. They are not already inside the $110–$195 planning range.

Many plants accept orders in ¼- or ½-yard increments. Confirm rounding and minimums with the supplier — we do not invent a single industry rule for that.

Bagged-mix prices

Shelf prices for 60 lb and 80 lb bags vary by store, city, and day. On November 19, 2026 we were not able to independently confirm a live, chain-wide Home Depot or Lowe’s price (those product pages blocked automated access). Angi mentions premixed bags from $4.50 to $27, a range too wide to use as a planning default because it appears to include specialty products.

The calculator therefore does not invent a national bag price. Enter what your local bag costs, and we multiply by the rounded-up bag count.

Installed project costs (driveways, patios, decks)

Installed prices are quoted per square foot and are a different number from ready-mix per yard. We keep them on the cost and comparison pages, not inside the volume calculator. Highlights, all cited on those pages:

Pavers, decks, tile — design notes we will not invent

City pages and “local” prices

Angi’s Houston, Los Angeles, and Tampa driveway pages (updated May 5, 2026) include a section titled “How Angi Gets Its Local Cost Data.” Angi starts with national average project costs, then applies local price index data from the U.S. Bureau of Economic Analysis, including Regional Price Parities (RPPs). Those figures are modeled from a national baseline, not a survey of local bids that we can re-run. We say so on the Texas, California, and Florida pages. Angi’s Orlando page (same date) uses different “How Angi Gets Its Cost Data” wording (customer surveys plus other research) and does not repeat the RPP paragraph; we quote that difference rather than assuming the same method.

Some Angi metro size tables are internally tight compared with the same page’s $8–$20/sf note and overall project range (Houston is the clearest example). We lead with the overall range and flag the inconsistency instead of “fixing” the table.

We do not invent a statewide average from one or two metros, and we do not apply a third-party “labor multiplier” table as if it were our own research.

What the volume estimate does not include

How we will update this

When we change a formula, a default, or a cited price range, we will update this page and the date above. Affiliate links or contractor-quote forms, when they exist, will be disclosed and will not change calculator math. The quote forms on the site are not live (they are marked TODO).